Construction and Fundraising Update Week of 2/22/16

Building for Health –Project Update
• All exterior wall framing is complete and window framing is in progress.
• Exterior insulation is in process.
• Roofing and roof insulation will occur over the next 10 days.
• Stairway to second floor is now available.
• Elevator installation is projected for June.

Building for Health –Fundraising Update
$885,000 of $2.2 million goal

Construction and Fundraising Update Week of 2/1/16

Building for Health –Project Update – Week of February 1, 2016.
• The structural steel frame of new building is complete, with inspections underway. Metal decking which is the base of the second floor is being installed.
• The exterior framework is in progress and being wrapped with vapor barrier over the top wall.
• The large crane has been removed and the site contractor is preparing to bring in structural fill for the first floor slab.
• A catch basin is being installed near the new main entrance.
• Conduits for electrical service have been installed. Underground connection is on hold until spring. In the meantime a pole transformer to run overhead lines to an existing pole is being discussed. This overhead feed would be removed once underground work is complete.
Visit the Photo Gallery at www.newlondonhospital.org/buildingforhealth for the latest construction photos.

Building for Health –Fundraising Update
$860,000 of $2.2 million goal. We continue to receive generous gifts from community supporters on a weekly basis. We are also in receipt of a $10,000 grant from the Brown Foundation of Texas.