| 10/06 |
Certificate of Need (CON) Application filed with New Hampshire Department of Health and Human Services Certificate of Need Board |
| 10/06 |
Preliminary site plan presented to Town of New London Planning Board |
| 1/07 |
CON application deemed complete. Hearing tentatively set for March 15, 2007 |
| 2/15/07 |
Board of the NH Health and Education Facilities Authority votes unanimously to approve a bond resolution authorizing the issuance of bond proceeds not in excess of $20 million for Building Towards the Future at New London Hospital. |
| 3/1/07 |
New London Hospital Board of Trustees approve unanimously to move forward with building project. |
| 3/14/07 |
John Shea, designee of the Governor and Council of the State of NH met with Tina Naimie and Bill Helm to review the project and the intent of NLH to issue bonds for part of the financing. Executive Councilor Shea found that the project meets an important need for our community and will present his findings to the Governor and Council for ratification on April 4. |
| 3/22/07 |
Dartmouth-Hitchcock Alliance Board unanimously approves the building project. |
| 4/9/07 |
NLH received unanimous approval from the Town of New London Zoning Board to grant the two outstanding variances for the BTTF project. the Board approved the height variance for the new building and the requested zoning variance for one of our additional parking areas. |
| 4/19/07 |
NLH
received unanimous verbal approval from the Department of Health and Human Services Certificate of Need Board (CON) for an expansion and renovation project estimated to cost $21 million. Final written approval is expected in June after the CON Board votes formally at its May meeting and the vote undergoes a 20-day public appeal process. |
| 4/24/07 |
NLH received final site plan approval from the Town of New London for our Building Towards the Future expansion and renovation project! |
| 6/14/07 |
Certificate of Need approval granted from state. |
| 6/15/07 |
Driveway permit issued from Town of New London Planning & Zoning Boards. |
| 7/2/07 |
Sitework for building project begins Parking Lot Phase A construction starts. Anticipated finish 8/1/07. |
| 7/2/07 - 8/20/07 |
Hospital Lower Level Renovations. |
| 8/30/07 |
4:00 p.m. - Building Towards The Future Groundbreaking Ceremony. |
| 8/07 - 11/07 |
Parking Expanded |
| 8/27/07 |
Foundation excavation begins for addition |
| 9/1/07 |
Renovations begin for Specialty Services |
| 9/04/07 – 9/17/08 |
Hospital Addition—site demolition, foundation excavation, structural steel, exterior framing, roofing, interior framing, new parking areas |
| 9/04/07 – 10/21/07 |
Temporary Specialty Services rooms in admin hall renovations |
| 2/27/08 – 8/13/08 |
New patient rooms & waiting area construction |
| 8/14/08 – 11/19/08 |
New Specialty Services area renovated |
| 11/19/08 |
Occupancy of new Specialty Services area |
| 9/19/08 – 10/08/08 |
Relocate MOB practices to addition |
| 10/09/08 – 12/24/08 |
Demolish front of MOB and site work; renovations to rear MOB |
| 11/20/08 – 11/24/08 |
Relocate med/surg to new patient rooms and former temporary Specialty Services rooms on admin hall |
| 11/25/08 – 3/18/09 |
Renovation of existing med/surg rooms |
| 3/18/09 |
Occupancy of renovated med/surg rooms |
| 2/05/09 – 4/22/09 |
South & West Lower Level renovations |
| 4/25/09 |
Occupancy of Lower Level |